序号 | 项目内容 | 全市合计 | 市本级 | 婺城区 | 金义新区(金东区) | 兰溪市 | 东阳市 | 义乌市 | 永康市 | 浦江县 | 武义县 | 磐安县 | 金华开发区 | 牵头单位 | |
1 | 新增老年助餐服务点60个 | 项目点位数 | 60 | / | 4 | 4 | 8 | 8 | 4 | 8 | 4 | 8 | 7 | 5 | 市民政局 |
平均进度(%) | 99.42% | / | 100% | 100% | 98.75% | 100% | 100% | 100% | 93.75% | 100% | 100% | 100% | |||
2 | 新增认知障碍照护专区床位600张 | 项目点位数 | 600 | 80 | 50 | 50 | 60 | 60 | 60 | 60 | 40 | 60 | 40 | 40 | 市民政局 |
平均进度(%) | 94.13% | 90% | 100% | 100% | 62.50% | 75% | 100% | 100% | 100% | 100% | 100% | 100% | |||
3 | 建设乡镇(街道)规范化老年学校33个 | 项目点位数 | 33 | / | 4 | 3 | 4 | 4 | 3 | 3 | 3 | 4 | 3 | 2 | 市教育局、市委老干部局 |
平均进度(%) | 87.73% | / | 85% | 90% | 90% | 90% | 95% | 90% | 90% | 73% | 90% | 90% | |||
4 | 建成村(社区)老年学堂245个 | 项目点位数 | 245 | / | 12 | 29 | 46 | 10 | 11 | 48 | 24 | 14 | 17 | 34 | 市教育局、市委老干部局 |
平均进度(%) | 84.27% | / | 76% | 80% | 90% | 90% | 95% | 86% | 80.42% | 60% | 80% | 90% | |||
5 | 新增政府举办村级医疗卫生机构100个 | 项目点位数 | 103 | / | 25 | 30 | 1 | 2 | 2 | 5 | 10 | 12 | 9 | 7 | 市卫生健康委 |
平均进度(%) | 75.58% | / | 95% | 40% | 90% | 100% | 100% | 95% | 52.50% | 100% | 96% | 96% | |||
6 | 新增规范化村级医疗卫生机构70个 | 项目点位数 | 71 | / | 7 | 11 | 13 | 15 | 9 | 5 | 6 | 3 | / | 2 | 市卫生健康委 |
平均进度(%) | 87.18% | / | 94% | 40% | 98.85% | 99% | 100% | 92% | 80.83% | 100% | / | 88% | |||
7 | 为全市8.8万名65岁以上本地户籍老年人免费接种肺炎疫苗 | 项目点位数 | 88000 | / | 7500 | 1000 | 14000 | 16700 | 14600 | 10800 | 7600 | 6800 | 3900 | 5100 | 市卫生健康委 |
平均进度(%) | 40% | / | 40% | 40% | 40% | 40% | 40% | 40% | 40% | 40% | 40% | 40% | |||
8 | 推进全市500家村卫生室(社区卫生服务站)配备使用国家带量采购药品 | 项目点位数 | 557 | / | 20 | 20 | 73 | 118 | 116 | 110 | 30 | 30 | 20 | 20 | 市医保局 |
平均进度(%) | 100% | / | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | |||
9 | 新(改)建农村公路45公里 | 项目点位数 | 45 | / | 6 | 4 | 5 | 8 | 5 | 4 | 3 | 5 | 5 | / | 市交通运输局 |
平均进度(%) | 93.08% | / | 90% | 100% | 100% | 100% | 98% | 100% | 90% | 75% | 100% | / | |||
10 | 新(改)建农村公交候车亭60个 | 项目点位数 | 60 | / | 10 | / | 10 | 5 | 6 | / | 7 | 10 | 12 | / | 市交通运输局 |
平均进度(%) | 78.50% | / | 40% | / | 100% | 100% | 100% | / | 75% | 60% | 90% | / | |||
11 | 治理堵点乱点10处 | 项目点位数 | 11 | / | 1 | 1 | 1 | 1 | 2 | 1 | 1 | 1 | 1 | 1 | 市交通运输局 |
平均进度(%) | 75.46% | / | 80% | 70% | 20% | 75% | 90% | 60% | 95% | 70% | 80% | 100% | |||
12 | 改造提升农村公路路口交通安全设施3000个 | 项目点位数 | 3001 | / | 201 | 298 | 400 | 503 | 350 | 400 | 150 | 400 | 99 | 200 | 市公安局、市交通运输局 |
平均进度(%) | 59.30% | / | 89% | 54% | 63.59% | 60% | 87% | 40% | 61.20% | 39% | 58% | 16% | |||
13 | 完成住宅小区充电网络配套改造25个以上 | 项目点位数 | 26 | / | 3 | 2 | 3 | 3 | 5 | 4 | 2 | 2 | 2 | / | 国网金华供电公司、市建设局 |
平均进度(%) | 87.50% | / | 95% | 95% | 95% | 95% | 100% | 40% | 95% | 95% | 95% | / | |||
14 | 新增公共充电枪2400个(其中农村1600个) | 项目点位数 | 2400(农村1600) | / | 100(农村100) | 390(农村390) | 250(农村70) | 380(农村190) | 510(农村305) | 230(农村150) | 210(农村135) | 90(农村35) | 50(农村35) | 190(农村190) | 市发改委 |
平均进度(%) | 99.34% | / | 99% | 100% | 100% | 100% | 100% | 100% | 95.19% | 100% | 100% | 100% | |||
15 | 新(改、扩)建公办中小学12所 | 项目点位数 | 12 | / | 1 | 1 | 1 | 1 | 2 | 1 | 1 | 1 | 1 | 2 | 市教育局 |
平均进度(%) | 92.08% | / | 90% | 70% | 95% | 95% | 93% | 100% | 100% | 75% | 95% | 100% | |||
16 | 义务教育段随迁子女就读公办学校达90% | 项目点位数 | 0.9 | / | 0.87 | 0.9 | 1 | 0.9 | 0.9 | 0.85 | 0.87 | 0.9 | 0.99 | 0.95 | 市教育局 |
平均进度(%) | 70% | / | 70% | 70% | 70% | 70% | 70% | 70% | 70% | 70% | 70% | 70% | |||
17 | 改造提升农村单村水站95座 | 项目点位数 | 95 | / | 29 | 6 | 14 | 3 | 3 | 11 | 3 | 12 | 14 | / | 市水利局 |
平均进度(%) | 100% | / | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | / | |||
18 | 新(改、扩)建农村生活污水处理设施270个 | 项目点位数 | 270 | / | 40 | 6 | 45 | 40 | 2 | 32 | 43 | 20 | 22 | 20 | 市建设局 |
平均进度(%) | 96.74% | / | 93% | 73% | 100% | 86% | 100% | 100% | 100% | 100% | 94% | 96% | |||
19 | 改造提升高标准农田(粮食生产功能区)1.165万亩 | 项目点位数 | 1.165 | / | 0.045 | 0.17 | 0.1 | 0.1 | 0.11 | 0.1 | 0.23 | 0.1 | 0.11 | 0.1 | 市农业农村局 |
平均进度(%) | 90.75% | / | 95% | 100% | 95% | 95% | 100% | 95% | 81.88% | 100% | 100% | 90% | |||
20 | 康复救助孤独症儿童320名 | 项目点位数 | 320 | / | 37 | 20 | 48 | 34 | 62 | 36 | 23 | 24 | 13 | 23 | 市残联 |
平均进度(%) | 91.50% | / | 95% | 90% | 90% | 95% | 90% | 95% | 90% | 90% | 90% | 90% | |||
21 | 新建“家门口青少年宫”10个 | 项目点位数 | 10 | / | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 团市委 |
平均进度(%) | 97.50% | / | 90% | 95% | 100% | 95% | 100% | 100% | 100% | 95% | 100% | 100% | |||
22 | 打造儿童友好公园30个 | 项目点位数 | 30 | / | 3 | 3 | 2 | 5 | 6 | 3 | 2 | 3 | 1 | 2 | 市建设局 |
平均进度(%) | 81% | / | 100% | 65% | 10% | 70% | 100% | 57% | 100% | 98% | 100% | 100% | |||
23 | 打造儿童友好医院30个 | 项目点位数 | 30 | / | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 市卫生健康委 |
平均进度(%) | 89.83% | / | 77% | 87% | 88.33% | 100% | 95% | 88% | 81.67% | 100% | 87% | 100% | |||
24 | 打造儿童友好学校30个 | 项目点位数 | 51 | / | 4 | 6 | 4 | 6 | 8 | 6 | 6 | 4 | 3 | 4 | 市教育局 |
平均进度(%) | 80.69% | / | 80% | 80% | 80% | 85% | 80% | 80% | 80% | 80% | 80% | 80% | |||
25 | 新增“浙里食安”示范食品作坊97家 | 项目点位数 | 97 | / | 5 | 10 | 17 | 10 | 10 | 10 | 10 | 10 | 5 | 10 | 市市场监管局 |
平均进度(%) | 76.29% | / | 80% | 80% | 80% | 70% | 70% | 70% | 80% | 70% | 70% | 84% | |||
26 | 建设中小学“示范学校食堂”120家 | 项目点位数 | 144 | / | 14 | 10 | 15 | 26 | 28 | 18 | 10 | 8 | 6 | 9 | 市市场监管局 |
平均进度(%) | 95% | / | 95% | 95% | 95% | 95% | 95% | 95% | 95% | 95% | 95% | 95% | |||
27 | 新增既有住宅加装电梯100台以上 | 项目点位数 | 105 | / | 15 | 12 | 12 | 12 | 12 | 12 | 8 | 8 | 2 | 12 | 市建设局 |
平均进度(%) | 94.38% | / | 93% | 87% | 95% | 98% | 100% | 58% | 100% | 95% | 90% | 100% | |||
28 | 创建省级高标准生活垃圾分类示范小区230个 | 项目点位数 | 230 | / | 40 | 19 | 26 | 30 | 40 | 17 | 10 | 13 | 5 | 30 | 市建设局 |
平均进度(%) | 77.15% | / | 78% | 75% | 85% | 80% | 76% | 60% | 31% | 85% | 85% | 90% | |||
29 | 住宅小区专业物业覆盖率达90% | 项目点位数 | 10 | / | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 市建设局 |
平均进度(%) | 92% | / | 80% | 100% | 95% | 100% | 100% | 70% | 95% | 95% | 90% | 95% | |||
30 | 创建三星级以上物业服务小区50个 | 项目点位数 | 50 | / | 5 | 8 | 4 | 5 | 8 | 4 | 2 | 6 | 1 | 7 | 市建设局 |
平均进度(%) | 42.84% | / | 40% | 40% | 40% | 40% | 55% | 40% | 40% | 44% | 40% | 40% | |||
31 | 启动城市社区嵌入式服务设施建设工程 | 项目点位数 | 1 | 1 | / | / | / | / | / | / | / | / | / | / | 市发改委 |
平均进度(%) | 95% | 95% | / | / | / | / | / | / | / | / | / | / | |||
32 | 向公众开放机关企事业单位体育场地设施200个 | 项目点位数 | 200 | / | 21 | 21 | 21 | 21 | 21 | 21 | 21 | 16 | 16 | 21 | 市体育局 |
平均进度(%) | 86.71% | / | 96% | 99% | 76.19% | 100% | 100% | 80% | 30% | 90% | 94% | 100% | |||
33 | 新建基层体育场地设施110个 | 项目点位数 | 110 | / | 22 | 9 | 20 | 7 | 8 | 10 | 8 | 11 | 7 | 8 | 市体育局 |
平均进度(%) | 93.01% | / | 83% | 93% | 95.25% | 99% | 100% | 85% | 91.25% | 100% | 100% | 100% | |||
34 | 新建“环浙步道”700公里以上 | 项目点位数 | 737 | / | 78 | 45 | 50 | 96 | 85 | 90 | 56 | 75 | 116 | 46 | 市体育局 |
平均进度(%) | 78.24% | / | 60% | 60% | 85% | 95% | 95% | 80% | 55% | 68% | 95% | 90% | |||
35 | 开展自救互助应知应会培训100万人以上 | 项目点位数 | 100.4 | / | 8.15 | 8.35 | 9.5 | 16.5 | 22.6 | 11 | 7.35 | 5.85 | 3.4 | 7.7 | 市应急管理局 |
平均进度(%) | 95% | / | 95% | 95% | 95% | 95% | 95% | 95% | 95% | 95% | 95% | 95% | |||
36 | 创建标准化规范化示范应急消防管理站20个 | 项目点位数 | 22 | / | 2 | 3 | 2 | 3 | 2 | 2 | 2 | 2 | 2 | 2 | 市应急管理局 |
平均进度(%) | 91.82% | / | 90% | 90% | 95% | 95% | 90% | 90% | 95% | 90% | 93% | 90% | |||
37 | 新建乡镇专职消防队10支 | 项目点位数 | 12 | / | 2 | / | 2 | 4 | / | / | / | / | 4 | / | 市消防救援支队 |
平均进度(%) | 85.83% | / | 75% | / | 90% | 90% | / | / | / | / | 85% | / | |||
38 | 达标提升乡镇专职消防队31支 | 项目点位数 | 37 | / | 1 | 7 | 7 | 7 | / | 10 | 2 | 3 | / | / | 市消防救援支队 |
平均进度(%) | 85.54% | / | 95% | 90% | 90% | 90% | / | 73% | 90% | 90% | / | / | |||
39 | 完成心肺复苏、溺水、交通事故等公众应急救护知识普及和技能培训20万人以上 | 项目点位数 | 200000 | / | 15800 | 14000 | 27000 | 34100 | 34900 | 24900 | 16000 | 13800 | 8500 | 11000 | 市红十字会 |
平均进度(%) | 95.50% | / | 100% | 100% | 60% | 100% | 100% | 95% | 100% | 100% | 100% | 100% | |||
40 | 完成应急救护持证人员培训5万人以上 | 项目点位数 | 50000 | / | 3900 | 3500 | 6560 | 8600 | 8800 | 6280 | 4030 | 3480 | 2120 | 2730 | 市红十字会 |
平均进度(%) | 92.50% | / | 100% | 100% | 65% | 100% | 100% | 100% | 100% | 100% | 80% | 80% |